1. Profile
(1) Project site:
Mu U Village, Dan Thanh Community, Duyen Hai District, Tra Vinh Province, Vietnam
(2) Owner:
Duyen Hai Power Generation Complex in Vietnam.
(3) Capacity:
Ultra-filtration 3×185 t/h+ one-stage RO 3×135 t/h+two-stage RO 3×143 t/h+mixed bed 2×188 t/h.
(4) Date of operation:
October 2015.
(5) Investment, construction and operation:
It was invested and operated by the Owner, designed and supplied by Wuhan Kaidi Water Services Co., Ltd. and China Chengda Engineering Co., Ltd. was the EPC contractor.
#1 and #2 two-stage RO Safety filter
2. Major environmental problems to be addressed
Desalination of sea water or treatment of surface water for boiler make-up water in power plants so as to save local fresh water resources.
3. Environmental standards and/or main index limits to be followed
Index of system water production: conductivity (25℃)≤0.15 μs/cm, silicon dioxide≤10 mg/L.
4. Technological process
Ultrafiltration + two-stage reverse osmosis + mixed bed (ion exchange).
5. Environmental pollution control effects
The water source of the project is the surface water from the upper reaches of La Bang Dam, and the main water quality indicators of the influent are: turbidity 10NTU, DS1485mg/L, CODMn5.8mg/L, activated silica 20.2mg/L; indicators of water produced by the system: conductivity (25℃)≤0.15μs/cm, silicon dioxide≤10 mg/L.
6. Social benefits
The implementation of the project improved the regional water environment quality and provided jobs for local residents.
7. Economic benefits
The implementation of the project could save about 13300 t/d of fresh water.
Project significance: The project can save fresh water resources and relieve fresh water shortage of the region.
All rights reserved copy or mirror SCO information cooperation platform
for environmental protection is prohibited without permission
Address: No.5 Hou Ying Fang Hutong, Xicheng District, Beijing
Postcode: 100035 ICP No.: Jing ICP 05009132